Planning Schedule/Scheduling Agreement from BELL
The Planning Schedule/Scheduling Agreement (PLS) is used as a way for Bell to place master purchase orders (blanket purchase orders). These are firm orders, and therefore, should not be mistaken as a forecast. You may notice more than one document with the same Scheduling Agreement #; make sure to use the
most recently sent document as updates may occur.

To view a Planning Schedule/Scheduling Agreement, select the document type‘ PLS’ from the document list page, click on the document number of the schedule you wish to view.

Details
Scheduling Agreement # The order number to be referenced on the
invoice.
Forecast Date The date the order was issued.
Horiz. Start Date Delivery date of the first fraction of the order.
Horiz. End Date Delivery date of the last fraction of the order.
Quantity Type Numeric value of cumulative quantity.
SRM GOA SRM GOA number.
Ship To Contains building no. used for delivery of materials.
Header Notes Supplier & buyer name.
Type Describes the confidence level in the orders quantities and delivery
date.
Timing Specifies intervals of the scheduled delivery dates (i.e. Daily,
Weekly, Monthly…).
Qty Specifies quantity of materials required for each interval.
Delivery Date Specifies the requested delivery date of the materials.
Line Notes Contains the ODS-MEPI and the Item price.